Engagement with residents and the wider public (via Commonplace) regarding the proposals for a dockless bike scheme in Haringey.
Review and analysis of feedback to help shape the proposed scheme.
Procurement
Spring 2023
-
Summer 2023
Engagement with prospective providers and agreeing terms and conditions.
Internal Consultation and Engagement
January 2023
-
August 2023
Proposals shared with internal stakeholders for comment and discussion, to help shape scheme.
Cabinet Decision
September 2023
-
Complete
The implementation of the dockless bike scheme, on a trial basis, approved by Cabinet decision on September 19, 2023.
Launch of dockless bike scheme
February 2024
-
Autumn 2025
Introduction of the the dockless bike scheme trial in Haringey.
Monitoring and review of dockless bike scheme
February 2024
-
Autumn 2025
Ongoing monitoring and review of how the scheme is running.